Every Risk Models are “wrong”

Every Risk Models are “wrong”
“Every risk model is wrong but some are useful” this famous remark by a statistician, George E. P. Box in 1976 is still valid in the world of project risk management.
His point was that we should focus more on whether something can be applied to everyday life in a useful manner rather than debating endlessly if an answer is correct in all cases.
Having seen Monte Carlo simulation for risk and range analysis performed for cost and schedule for multibillion dollars, the multi-year project came with the result of less than 5% cost contingency and a few weeks in schedule contingency. We had to send the project team home and ask them to come back with a more realistic view of the project.
Setting overly optimistic expectations with stakeholders is simply bad business and a clear sign that your risk model is not as comprehensive as it should be.
Implementing an effective risk model can improve your chances of successfully delivering a project on time and within budget. This is because once all risks have been carefully assessed, you can make more accurate project estimates – both in terms of scope, time and cost.
While there’s no fancy tool that can replace true professional, experienced judgement, a robust risk model will be an invaluable tool throughout the project life-cycle.
What is your experience with project risk models and range analysis?
Love to hear your story in the comments below.
explore more insights
all insights

S-Curve in Project Management

S-Curve in Project Management
If you are a project manager, you may have heard of S-Curve, which shows progress, cost, manhours, and quantity. As said, “trend is your friend”, most Project Managers are interested in seeing S-curves in project reports.
S-Curve is a mathematical graph or illustration that properly illustrates the appropriate cumulative data for a project or task. This data can be the cost or man-hours plotted against time.
The reason why it’s called an S curve is not a very technical one. It’s because of the S-shape that the graph makes. The shape, however, depends on the type of project, so other formations are possible.
Some of the most common uses for s-curves are measuring progress, evaluating performance, and making cash-flow forecasts.
Why an “S”?
The S-Curve often forms its shape because the growth of the project in the beginning stages is usually slow. As more progress is made, the growth accelerates rapidly, creating an upward slope that forms the middle part of the “S.”
After the midpoint, the growth begins to plateau, is because the project is mostly finished at this point and is winding down — typically only tasks such as finishing touches and final approvals are left at this point.
Banana Curve
Once your baseline S-curve is created, you can play with the inputs to identify the impact on the project.
The most common example is plotting the earliest and latest start dates for tasks in your project schedule. These two S-curves typically overlap at the beginning and end of the project, producing a banana-shaped curve known as “Banana Curves”. The banana shape envelope of the early and late curves represents the range of possibilities that the project can expect if it is completed on time.
Project managers often estimate the earliest, and latest, a task can start in the schedule while not affecting the overall duration. This indicates how much flex or ‘float’ there is in the schedule should things change during project execution.
As actual work is delivered, you can plot this against the banana curve. If the data points are close to the ‘latest date’ curve, it flags the risk of project delay and prompts the project team to take action.
S–Curve helps
  • to track the project status
  • to make predictions about project progress, performance, cost, resources and quantity
  • to prepare you for upcoming risks and opportunities
  • to compare baseline vs. current status
Let’s make use of the S curve to predict the project’s future. Need help? Explore how zerofloat can help you control your project.
explore more insights
all insights

Critical Path vs Critical Chain

Critical Path vs Critical Chain
Critical Path vs Critical Chain: Are You Managing Time, or Managing Flow?

In the world of project controls, two terms often pop up when it comes to scheduling: Critical Path Method (CPM) and Critical Chain Project Management (CCPM). While both aim to keep projects on track, they tackle the problem from very different angles.

Critical Path focuses on the longest path of dependent tasks—delays here directly impact the project end date. It’s all about identifying task sequences and managing float (or the lack of it).

Critical Chain, on the other hand, brings in a human element—acknowledging resource constraints and the tendency to pad task durations. Instead of stacking buffers throughout the schedule, CCPM pulls them together at key points, protecting the project timeline with smarter focus and less multitasking.

Key differences:
CPM = Task-driven, deterministic, static.
CCPM = Resource-driven, probabilistic, adaptive.

At zerofloat, we often ask clients:
Are you simply tracking tasks, or are you building flow and resilience into your delivery?

Which method has worked better for you in real-world projects—and why?

Let’s compare notes in the comments.

Drop your thoughts below and feel free to repost.
Need help? Explore how zerofloat can help you control your project.
explore more insights
all insights

Top 5 Myths About Project Forecasting

Top 5 Myths About Project Forecasting
🚨 Top 5 Myths About Project Forecasting – BUSTED

🔮 Project controllers are often seen as the fortune tellers and forecasters of project performance. But not all predictions are created equal… and not all assumptions hold up.

Which forecasting myth do we need to be most aware of?

Here are the Top 5 myths that continue to trip up even experienced teams:

1. “Once the baseline is approved, forecasts won’t change much”
Myth: The original project plan is accurate enough, and forecasts should stay close to it.
Reality: Forecasts must continuously evolve. Changes in scope, resource availability, market conditions, and productivity mean that forecasts should be dynamic, not static.

2. “Earned Value gives you all the answers”
Myth: Earned Value Management (EVM) provides a complete and reliable forecast on its own.
Reality: While EVM is powerful, it doesn’t account for future risks, productivity trends, or changes in execution strategy. Forecasting requires contextual inputs beyond CPI and SPI.

3. “Forecasting is just guessing with numbers”
Myth: Forecasts are speculative and unreliable, so there’s little point in refining them.
Reality: Forecasts are educated predictions based on data, trends, and performance. With good inputs and regular updates, they are critical tools for proactive decision-making.

4. “You only need to re-forecast when something goes wrong”
Myth: Forecasting is a reactive process triggered by major issues.
Reality: Forecasting should be a proactive, regular discipline—not just a response to crisis. Early identification of trends enables timely corrective actions.

5. “More detail means a better forecast”
Myth: The more detailed your schedule and cost model, the more accurate your forecast.
Reality: Excessive detail can obscure key trends and slow down updates. A forecast must balance accuracy, timeliness, and relevance. Focus on what’s driving the outcomes.

Which myth have you encountered the most? Add your experience or share this with your team. Feel free to repost 🔁
Need help? Explore how zerofloat can help you control your project.
explore more insights
all insights

Shift your perspective

Shift your perspective
“If you think you are going in a circle, just shift your perspective.” In the realm of project delivery, it’s not uncommon to find ourselves trapped in a repetitive cycle of stagnation.
However, breaking free from this cycle is possible through a simple shift in perspective.
Explores the power of perspective in project management and emphasises the need to recognise the loop and challenge assumptions. Seeking diverse inputs, fostering a learning culture, embracing disruption, and emphasising agile methodologies are key strategies to unlock fresh perspectives.
By adopting a growth mindset and embracing change, project teams can break free from the constraints of routine and open themselves up to transformative outcomes.
So, the next time you find yourself going in circles, remember that a shift in perspective holds the key to breaking free and achieving project success.
Need help? Explore how zerofloat can help you control your project.
explore more insights
all insights

Transforming project controls

Transforming project controls
What do we do in project controls?
Many professionals still struggle to understand project controls real value add to project success.
It is simple,
Project controls provide 3 things: 1.      Early warning 2.      Accurate forecast and 3.      Effective change and risk control
Project controls, it is all about providing the right information, at the right level to assist project leaders to make the right decisions.
Project controllers may not have a crystal ball that can predict the project’s future but have tools and expertise that can help to make the right decision, at right time.
The world is changing fast.
  • Industry standards are changing.
  • Regulations are changing.
  • Technology is changing.
  • The nature, size and complexity of projects are changing.
  • The way we control the project is changing.
4D,5D, AI, RPA, AR, VR, BigData, RFID, Drones …these are not just fancy hi-tech words anymore, but it is becoming a reality.
  • Use of Artificial Intelligence (AI) and Robotic Process Automation (RPA) for routine tasks,
  • Augmented Reality (AR) and Virtual Reality (VR) for design and constructability reviews,
  • Big Data for Analytics and dashboards,
  • Radio Frequency Identifier (RFID) for material, logistics and inventory control,
  • Drones are used for site surveys and progress tracking …
But remember decision-making is still done by humans in the project world.
Transforming project controls is all about professionalising this rapidly growing profession, bringing the community together, sharing lessons learnt and contributing towards its continuous improvement.
We know that billions of dollars are wasted every year due to poor project performance.
Let’s add value by effective use of Project Controls.
Let’s contribute to society by delivering projects successfully.
Need help? Explore how zerofloat can help you control your project.
explore more insights
all insights

Triple constraint

Triple constraint
The Classical Triple Constraint model includes Cost, Time and Scope. The enhanced model includes an additional three constraints Quality, Benefits and Risk. Safety is a non-negotiable element.
Is that the Triple Constraint (six in the modern world) really useful for measuring project success or evaluating competing demands?
If you need to compromise on one, which one will be your pick? Not an easy answer.
That reality is also expressed as the pick two principle, which maintains that for any given set of three desired qualities or expectations — such as “good, fast and cheap” — it is likely that only two can coexist: A given product/project might be delivered quickly and inexpensively, for example, but the quality will suffer.
More often, a project manager needs to weigh one constraint against another to reach the best result and when the project is balanced well will lead to success.
What is your experience in managing a successful project?
Need help? Explore how zerofloat can help you control your project.
explore more insights
all insights

Project Controls is a Waste of Money

Project Controls is a Waste of Money
“Project Controls is a Waste of Money – Unless You Actually Use It”

Companies spend millions on fancy project controls systems, detailed schedules, cost forecasts, and risk registers—only to ignore them when making decisions. What’s the point?

If your leadership treats Project Controls as a reporting function instead of a decision-making tool, you’re just burning cash.

Here’s how Project Controls is wasted every day:
❌ Schedules that are updated but not followed.
❌ Risk registers that exist for audits, not action.
❌ Cost forecasts that are ‘adjusted to fit’ instead of exposing the truth.
❌ Teams that deliver reports but don’t influence decisions.
Project Controls is not about producing reports. It’s about controlling projects.

👉 If your Project Controls team isn’t helping shape strategy, challenge unrealistic plans, and drive accountability, then yes—it is a waste of money.

But when used properly? It’s the difference between a successful project and a disaster.

Here’s how Project Controls is used wisely to add value every day:
✅ Decision-making tool
✅ Helping shape strategy and plans
✅ Challenge unrealistic plans
✅ Drive accountability
✅ Don’t overcomplicate things
✅ Don’t sit on the sidelines

So, be honest—is your organisation using Project Controls effectively, or just paying for expensive theatre?

Drop your thoughts below and feel free to repost.
Need help? Explore how zerofloat can help you control your project.
explore more insights
all insights

Planning vs. Scheduling

Planning vs. Scheduling
Planning defines WHAT and HOW, while Scheduling defines WHEN and WHO.
Let’s look at Planning vs. Scheduling by understanding the Key Differences and Best Practices.
In project management, planning and scheduling are two closely related but fundamentally different processes. Understanding their distinctions is crucial for effective project execution. Simply put:
  • Planning defines WHAT and HOW a project will be executed.
  • Scheduling defines WHEN and WHO will perform the tasks.
Both are essential for ensuring that projects meet their objectives within time, cost, and quality constraints.

The Role of Planning in Project Management

Planning is the foundation of a successful project. Because projects are of finite duration and often involve unique work processes, meticulous planning ensures that all aspects are well thought out before execution begins.
The project plan serves as a formal document that guides the project team by detailing: Project Scope: Defines the boundaries of the project, including objectives and deliverables. Tasks and Work Breakdown Structure (WBS): Breaks down the project into manageable components. Resources and Budget Allocation: Identifies required resources, estimated costs, and funding sources. Risk Management Plan: Identifies potential risks and mitigation strategies. Project Success Criteria: Outlines measures for cost, quality, and schedule performance.

Best Practices for Effective Planning

Define Clear Objectives: Ensure all stakeholders agree on project goals and success criteria. Engage Key Stakeholders Early: Collaboration ensures alignment with business needs. Break Down the Work: Use a Work Breakdown Structure (WBS) to organise tasks. Identify Dependencies and Risks: Proactively address constraints and uncertainties. Establish a Change Control Process: Ensure flexibility while maintaining control over scope changes.

The Role of Scheduling in Project Management

Once the project plan is in place, scheduling determines the timing and sequencing of activities. The project schedule is a time-based roadmap that ensures tasks are completed in the right order and within the set timeframe.
Key elements of scheduling include: Activity Sequencing: Establishes task dependencies (e.g., finish-to-start, start-to-start relationships). Duration Estimation: Determines how long each activity will take. Resource Allocation: Assigns specific team members and assets to tasks. Milestones and Deadlines: Defines key project checkpoints and completion dates. Schedule Constraints: Accounts for external dependencies, resource availability, and project deadlines.

Best Practices for Effective Scheduling

Use a Scheduling Tool: Leverage software like Primavera P6, Microsoft Project, or similar tools to maintain accuracy. Set Realistic Durations: Base time estimates on historical data and expert judgment. Optimise Resource Allocation: Ensure workloads are balanced and avoid resource over-allocation. Account for Contingencies: Include buffer time for high-risk activities. Continuously Monitor and Adjust: Track progress and adjust the schedule as needed to meet project objectives.

Planning vs. Scheduling: A Complementary Approach

While planning and scheduling serve different purposes, they are inherently connected. A well-developed project plan ensures that the schedule is realistic and achievable, while an effective schedule ensures that the plan is executed efficiently. Together, they provide a roadmap for project success, balancing scope, time, and resource constraints.
By following best practices in both planning and scheduling, project managers can enhance project performance, reduce risks, and achieve objectives effectively. Whether managing a large-scale infrastructure project or a small internal initiative, integrating sound planning and scheduling techniques is key to delivering success.
Need help? Explore how zerofloat can help you control your project.
explore more insights
all insights

DCMA 14-point Schedule Assessment

DCMA 14-point Schedule Assessment
DCMA 14-point Schedule Assessment is a project management guideline established on 14 metrics that provide the possibility to make a qualitative and quantitative evaluation of the schedule. The DCMA (Defense Contract Management Agency) introduced it in 2005 to ensure projects worth over 20 million dollars were following best practice guidelines in the US Defence Department.
The DCMA 14-Point Assessment
1. Logic – Is the schedule logical? Schedule logic involves scheduling tasks; Are all the predecessor, and successor tasks concurrent? Missing links need to be resolved because without schedule logic an accurate Critical Path will not be possible. The number of activities that are missing a predecessor, a successor or both should not exceed 5% of the activities within the schedule.
2. Leads – are not allowed in scheduling as they are confusing and disrupt the flow of the schedule. Leads are often replaced with positive lags, but this isn’t always the best alternative. It is better to have shorter known scopes of work tasks connected by FS relationships, with no lags. The DCMA requires no leads (0%)
3. Lags – The DCMA does allow positive lags but has set a limit for use in a schedule. The limit for lags is no more than 5% of activity relationships. The best option is to replace lags with tasks describing the effort or process, such as cure time. Lags are limited to 5% in order to support schedule clarity. The total number of activities with lags should not exceed 5% of the activities within the schedule.
4. FS Relationships – Even though Primavera P6 and Deltek Acumen Fuse both support all relationship types, the DCMA assessment states that 90% (or more) of schedule dependencies should be Finish-Start (FS). Start-Start (SS) are acceptable, but building a whole schedule using SS is obviously unacceptable. The total number of activities with Finish to Start (FS) logic links >90%. Non-typical tasks are limited to <10 % of total tasks.
5. Hard Constraints – can really affect logic and disable a schedule from being logic-driven. The DCMA assessment states that hard constraints should be limited to 5% of uncompleted tasks. Constraints of any type are discouraged and a schedule should work without any.
6. High Float – activities may not be linked properly and can cause stress on the Critical Path. Total Float values are limited to 44 days, therefore review tasks that have greater than 2 months of total float and limit their usage to 5% of incomplete tasks.
7. Negative Float – Schedules that have negative float tasks are already behind. Ideally, the DCMA says to avoid having a negative float in your schedule. If there is a negative float, make sure it is accompanied by a documented plan to mitigate being late.
8. High Duration Tasks – Limit long-duration tasks to 5% of incomplete tasks. Task durations should be no longer than two months in order to support schedule updating and reporting efforts. Break long activities down into a series of shorter ones for more detail.
9. Invalid Dates – Forecasted (future work) work should not be in the past and actual (completed work) work should not be in the future. Invalid dates are not allowed under any circumstance; this will avoid illogical situations where future work is planned for the past and completed work happened in the future.
10. Resources – Resource loading is not a requirement, but the DCMA like schedules to be resource and cost-loaded. If you follow this path make sure the resource-loaded schedule is completely loaded. All activities except milestones must have a cost or associated resource.
11. Missed Tasks – This check looks at how many activities have finished late compared to the baseline date, monitoring excessive slippage. Only 5% of activities can slip from their finish baseline dates. This metric is a conservative and retrospective measure of schedule progress, but it’s a good generic check to see if your project will deliver on time or not.
12. Critical Path Test – ensures the schedule has one continuous linkage from project start to finish. It tests the integrity of a schedule’s Critical Path, looking for fluidity driven by good logic linking.
13. Critical Path Length Index (CPLI) is a forward-looking gauge that assesses the required efficiency to complete the project on schedule. It measures the ratio of the project critical path length and the project total float to the project critical path length. The critical path length is the time in workdays from the current date to the completion of the project. The target number is 1.0 and schedules that have a CLPI less than 0.95 require further review.
14. Baseline Execution Index (BEI) is an early warning indicator that a schedule is in trouble of not meeting the deadline. Most scheduling software doesn’t have a BEI variable, but it is possible to compute the ratio yourself or purchase an additional scheduling software supplement. The BEI ratios advanced, nontrivial, and purposeful warning makes the computation worth the effort. A BEI of 1.0 means that the schedule is on the right track.
In summary
The DCMA 14-Point assessment is a rigorous set of schedule quality guidelines. Schedules submitted to the DoD have to pass this assessment before projects are approved. Although this assessment was originally introduced for DoD schedules, it has become an industry-standard metric and is a useful resource for understanding best scheduling practices.
Although the DCMA 14-Point assessment offers a comprehensive schedule inspection that provides an analysis of schedule quality, there are no guarantees that your project outcome will be successful.
While satisfying these guidelines doesn’t necessarily mean the schedule is feasible, the project still needs to schedule the full scope and understand execution and logic; not satisfying them almost certainly means it is not.